Martin Cameron to ask the Minister for Roads and Road Safety — 

With reference to the upgrade of the Lloyd Street and Waterloo Road intersection in Moe:

(1) When will the required utility service relocations be completed.
(2) Has the acquired land for the proposed upgrade been finalised.
(3) When will the pre-construction activities be finalised.
(4) When will construction dates be confirmed.

Answer - 1 August 2025

I thank the member for his question.

 

1)      The required telecommunication service relocations have been completed. Designs and approvals of other utility services, including water and power, have been finalised with their relocation to occur along with the road construction works.

2)      Land acquisition is currently being finalised with possession of the required private land available when required.

3)      Other pre-construction activities, primarily working with V/Line to incorporate the required railway signals and road designs, are progressing.

4)      The Department of Transport and Planning (DTP) will continue to keep the community informed as pre- construction activities are finalised and construction dates are confirmed.

 

A signature on a white background  AI-generated content may be incorrect.

 

Hon Melissa Horne MP

Minister for Health Infrastructure

Minister for Ports and Freight

Minister for Roads and Road Safety

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

View all questions
• Answered
Asked
14 May 2025
by Cameron, Martin
Due
13 June 2025
Answered
1 August 2025