With reference to the upgrade of the Lloyd Street and Waterloo Road intersection in Moe:
(1) When will the required utility service relocations be completed.
(2) Has the acquired land for the proposed upgrade been finalised.
(3) When will the pre-construction activities be finalised.
(4) When will construction dates be confirmed.
I thank the member for his question.
1) The required telecommunication service relocations have been completed. Designs and approvals of other utility services, including water and power, have been finalised with their relocation to occur along with the road construction works.
2) Land acquisition is currently being finalised with possession of the required private land available when required.
3) Other pre-construction activities, primarily working with V/Line to incorporate the required railway signals and road designs, are progressing.
4) The Department of Transport and Planning (DTP) will continue to keep the community informed as pre- construction activities are finalised and construction dates are confirmed.
Hon Melissa Horne MP
Minister for Health Infrastructure