Committee Home PageTable Of ContentsPrevious PageNext Page

APPENDIX E OPTIONS COSTING ANALYSIS FOR VICTORIAN PORTS

Ruler

This costing analysis was prepared for the Environment and Natural Resources Committee by Ms Lyn McIlwain, Consultant, Ports & Maritime Environmental Consultancy Services, Golder & Associates Ltd.

Port of Melbourne - Option 1

Option 1
The vessel leaves the port and exchanges ballast at sea before returning to load.

Distance
40 nautical miles (nm) -one-way from Fawkner Beacon to nearest area of 60m depth. Fawkner Beacon is the Fairway beacon for the port of Melbourne.

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

Deadweight

35 616dwt

45 262dwt

37 700dwt

101 900dwt

Gross Tonnage

32 534t

26 092t

26 162t

65 094t

Charter Ratea.

$25 000

$13 500

$19 500

$36 000

Exchange timeb.

53hrs

51hrs

33hrs

45hrs

Pilotage Timec.

8hrs

10hrs

10hrs

10hrs

Tot. Voy. Timed.

61hrs

61hrs

43hrs

55hrs

Daily Fuel Cons.

57 t

24.9 t

28 t

61 t

Ball. Capacitye

12 466m3

20 368m3

13 195m3

35 665m3

Ball. P/p Cap.f

700 m3/hr

1 200 m3/hr

1 200 m3/hr

2 400 m3/hr

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete an exchange of ballast water where 3 times the volume of ballast water is pumped through the tanks.
c. Pilotage has been calculated from berth to 60m depth area just beyond the pilot boarding ground and back to the berth.
d. Time taken to exchange ballast plus pilotage time.
e. Approximate ballast capacity only.
f. Combined pumping capacity of both ballast pumps.

Port of Melbourne - Option 1 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

3 688

3 213

3 215

4 383

Moor/unmoor

1 150

1 150

1 150

1 750

Linesboata.

375

375

375

1 070

Tugsb.

5 120

5 250

5 120

12 400

Channel duesc.

13 014

10 437

10 465

26 038

Fueld.

18 834

8 227

6 522

18 173

Voyage Cost

63 542

34 313

34 938

82 500

Exchange coste.

2 106

1 620

1 630

4 500

         

TOTAL

107 829

64 585

63 415

150 814

a. 1 lines boat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker.
b. Calculated to allow 1 tug for each of the first three categories and 2 tugs for the crude oil tanker (tug charges calculated to include letting go and re-berthing after returning from ballast water exchange).
c. Assuming this fee will be charged again upon re-entry into the port.
d. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
e. Cost of running the ballast pumps for the duration of the exchange. (This includes additional maintenance).

Port of Melbourne - Option 2

Option 2
The vessel loads cargo to its marks or maximum stability criteria, returns to sea to dump all ballast, then returns to port to complete loading.

Distance
40 nm (one-way from Fawkner Beacon to nearest area of 60m depth).

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

         

Deadweight

35 616dwt

45 262dwt

37 700dwt

101 900dwt

Gross Tonnage

32 534t

26 092t

26 162t

65 094t

Charter Ratea.

$25 000

$13 500

$19 500

$36 000

Discharge timeb.

18hrs

17hrs

11hrs

15hrs

Pilotage Timec.

8hrs

10hrs

10hrs

10hrs

Tot. Voy. Timed.

26hrs

27hrs

21hrs

25hrs

Daily Fuel Cons.

57 t

24.9 t

28 t

61 t

Ball. Capacitye.

12 466 m3

20 368 m3

13 195 m3

35 665 m3

Ball. P/p Cap.f.

700 m3/hr

1 200 m3/hr

1 200 m3/hr

2 400 m3/hr

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete discharging full load of ballast.
c. Pilotage has been calculated from berth to 60m depth area just beyond the pilot boarding ground and back to the berth.
d. Time taken to dump ballast plus pilotage time.
e. Approximate ballast capacity only.
f. Combined pumping capacity of both ballast pumps.

Port of Melbourne - Option 2 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

3 688

3 213

3 215

4 383

Moor/unmoor

1 150

1 150

1 150

1 750

Linesboata.

375

375

375

1 070

Tugsb.

5 120

5 250

5 120

12 400

Channel duesc.

13 014

10 437

10 465

26 038

Fuel ($130/t)d.

8 028

3 642

4 247

8 260

Voyage Cost

27 083

15 188

17 063

37 500

Discharge coste.

702

540

543

1 500

         

TOTAL

59 160

39 795

42 178

92 901

a. 1 lines boat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker.
b. Calculated to allow 1 tug for each of the first three categories and 2 tugs for the crude oil tanker (tug charges calculated to include letting go and re-berthing after returning from ballast water exchange).
c. Assuming this fee will be charged again upon re-entry into the port.
d. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
e. Cost of running the ballast pumps for the duration of the de-ballast. (This includes additional maintenance).

There may be an additional cost with this Option caused by any delay of the vessel if the berth is not immediately available upon the vessel's return to port (i.e., another vessel has arrived and taken up the berth). This is particularly so in the case of container vessels at busy terminals.

Port of Melbourne - Option 3

Option 3
The vessel loads cargo to its marks or maximum stability criteria then moves to a berth designated for off-loading contaminated ballast into shore holding tanks, before returning to the original cargo berth to complete loading

Distance
Furthest distance would be a maximum pilotage time of 2 hours. In this instance, distance is calculated as pilotage time owing to speed limits within the respective channels/river (This will cause the vessel's speed to vary over this distance).

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

         

Deadweight

35 616dwt

45 262dwt

37 700dwt

101 900dwt

Gross Tonnage

32 534t

26 092t

26 162t

65 094t

Charter Ratea.

$25 000

$13 500

$19 500

$36 000

Discharge timeb.

18hrs

17hrs

11hrs

15hrs

Pilotage Timec.

4hrs

4hrs

4hrs

4hrs

Tot. Voy. Timed.

22hrs

21hrs

15hrs

19hrs

Daily Fuel Cons.

57 t

24.9 t

28 t

61 t

Ball. Capacitye

12 466 m3

20 368 m3

13 195 m3

35 665 m3

Ball. P/p Cap.f.

700 m3/hr

1 200 m3/hr

1 200 m3/hr

2 400 m3/hr

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete discharging full load of ballast to shore.
c. Pilotage has been calculated at a maximum of 2 hours each way.
d. Time taken for a return trip from facility back to berth plus time taken to completely de-ballast.

Port of Melbourne - Option 3 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

1 042

1 042

1 042

1 042

Moor/unmoor

2 300

2 300

2 300

3 500

Lines boata.

750

750

750

2 140

Tugsb.

10 240

10 240

10 240

24 800

Channel duesc.

13 014

10 437

10 465

26 038

Fuel ($130/t)d.

1 235

540

607

1322

Voyage Cost

22 917

11 813

12 188

28 500

Discharge coste.

702

540

543

1 500

TOTAL

52 200

37 662

38 135

88 842

a. 1 lines boat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker. For this Option there will be two arrivals.
b. Calculated to allow 1 tug for each of the first three categories and 2 tugs for the crude oil tanker (tug charges calculated to include letting go and re-berthing after returning from ballast water exchange). Again, two arrivals are allowed.
c. Assuming this fee will be charged again upon re-entry into the port.
d. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
e. Cost of running the ballast pumps for the duration of the de-ballast. (This includes additional maintenance).

There may be an additional cost with this Option caused by any delay of the vessel if the berth is not immediately available upon the vessel's return to port (i.e., another vessel has arrived and taken up the berth). This is particularly so in the case of container vessels at busy terminals.

This Option also assumes that all vessels will have a shore discharge ballast manifold retro-fitted and are able to part-load cargo while retaining all ballast on-board until berthed at shore facility.

Port of Geelong - Option 1

Option 1
The vessel leaves the port and exchanges ballast at sea before returning to load.

Distance
48.7 nm (one-way from Corio Bay Tanker Berth to nearest area of 60m depth via the South Channel).

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

         

Deadweight

 

45 262dwt

37 700dwt

101 900dwt

Gross Tonnage

 

26 092t

26 162t

65 094t

Charter Ratea.

 

$13 500

$19 500

$36 000

Exchange timeb.

 

51hrs

33hrs

45hrs

Pilotage Timec.

 

10hrs

10hrs

10hrs

Tot. Voy. Timed.

 

61hrs

43hrs

55hrs

Daily Fuel Cons.

 

24.9 t

28 t

61 t

Ball. Capacitye

 

20 368 m3

13 195 m3

35 665 m3

Ball. P/p Cap.f

 

1 200 m3/hr

1 200 m3/hr

2 400 m3/hr

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete an exchange of ballast water where 3 times the volume of ballast water is pumped through the tanks.
c. Pilotage has been calculated from berth to 60m depth area just beyond the pilot boarding ground and back to the berth.
d. Time taken to exchange ballast plus pilotage time.
e. Approximate ballast capacity only.
f. Combined pumping capacity of both ballast pumps.

Port of Geelong - Option 1 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

 

3 213

3 215

4 383

Moor/unmoor

 

1 150

1 150

1 750

Linesboata.

 

375

375

1 070

Tugsb.

 

5 250

5 120

12 400

Channel duesc.

 

10 437

10 465

26 038

Fuel ($130/t)d.

 

8 227

6 522

18 173

Voyage Cost

 

34 313

34 938

82 500

Exchange coste.

 

1 620

1 630

4 500

         

TOTAL

 

64 585

63 415

150 814

a. 1 linesboat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker.
b. 1 tug allowed for each of the first three categories, 2 tugs allowed for the crude oil tanker (tug charges calculated to include letting go and re-berthing after returning from ballast water exchange).
c. Assuming this fee will be charged again upon re-entry into the port.
d. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
e. Cost of running the ballast pumps for the duration of the exchange. (This includes additional maintenance).

Port of Geelong - Option 2

Option 2
The vessel loads cargo to its marks or maximum stability criteria, returns to sea to dump all ballast, then returns to port to complete loading.

Distance
48.7 nm (one-way from Corio Bay Tanker Berth to nearest area of 60m depth via the South Channel).

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

         

Deadweight

 

45 262dwt

37 700dwt

101 900dwt

Gross Tonnage

 

26 092t

26 162t

65 094t

Charter Ratea.

 

$13 500

$19 500

$36 000

Discharge timeb.

 

17hrs

11hrs

15hrs

Pilotage Timec.

 

10hrs

10hrs

10hrs

Tot. Voy. Timed.

 

27hrs

21hrs

25hrs

Daily Fuel Cons.

 

24.9 t

28 t

61 t

Ball. Capacitye

 

20 368 m3

13 195 m3

35 665 m3

Ball. P/p Cap.f.

 

1 200 m3/hr

1 200 m3/hr

2 400 m3/hr

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete discharging full load of ballast.
c. Pilotage has been calculated from berth to 60m depth area just beyond the pilot boarding ground and back to the berth.
d. Time taken to dump ballast plus pilotage time.
e. Approximate ballast capacity only.
f. Combined pumping capacity of both ballast pumps.

Port of Geelong - Option 2 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

 

3 213

3 215

4 383

Moor/unmoor

 

1 150

1 150

1 750

Linesboata.

 

375

375

1 070

Tugsb.

 

5 250

5 120

12 400

Channel duesc.

 

10 437

10 465

26 038

Fuel ($130/t)d.

 

3 642

4 247

8 260

Voyage Cost

 

15 188

17 063

37 500

Discharge coste.

 

540

543

1 500

         

TOTAL

 

39 795

42 178

92 901

a. 1 lines boat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker.
b. Calculated to allow 1 tug for each of the first three categories and 2 tugs for the crude oil tanker (tug charges calculated to include letting go and re-berthing after returning from ballast water exchange).
c. Assuming this fee will be charged again upon re-entry into the port.
d. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
e. Cost of running the ballast pumps for the duration of the de-ballast. (This includes additional maintenance).

There may be an additional cost with this Option caused by any delay of the vessel if the berth is not immediately available upon the vessel's return to port (i.e., another vessel has arrived and taken up the berth). This is particularly so in the case of container vessels at busy terminals.

Port of Geelong - Option 3

Option 3
The vessel loads cargo to its marks or maximum stability criteria then moves to a berth designated for off-loading contaminated ballast into shore holding tanks, before returning to the original cargo berth to complete loading

Distance
Farthest distance would be maximum pilotage time of 4 hours.

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

         

Deadweight

 

45 262dwt

37 700dwt

101 900dwt

Gross Tonnage

 

26 092t

26 162t

65 094t

Charter Ratea.

 

$13 500

$19 500

$36 000

Discharge timeb.

 

17hrs

11hrs

15hrs

Pilotage Timec.

 

8hrs

8hrs

8hrs

Tot. Voy. Timed.

 

25hrs

19hrs

23hrs

Daily Fuel Cons.

 

24.9 t

28 t

61 t

Ball. Capacitye

 

20 368 m3

13 195 m3

35 665 m3

Ball. P/p Cap.f.

 

1 200 m3/hr

1 200 m3/hr

2 400 m3/hr

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete discharging full load of ballast.
c. Pilotage has been calculated at a maximum of 4 hours each way.
d. Time taken for a return trip from facility back to furthest berth including time taken to discharge ballast.

Port of Geelong - Option 3 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

 

1 636

1 638

2 016

Moor/unmoor

 

2 300

2 300

3 500

Linesboata.

 

750

750

2 140

Tugsb.

 

10 240

10 240

24 800

Channel duesc.

 

10 437

10 465

26 038

Fuel ($130/t)d.

 

1 079

1 213

2 643

Voyage Cost

 

14 063

15 438

34 500

Discharge coste.

 

540

543

1 500

         

TOTAL

 

41 045

42 587

97 137

a. 1 lines boat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker. For this Option there will be two arrivals.
b. Calculated to allow 1 tug for each of the first three categories and 2 tugs for the crude oil tanker (tug charges calculated to include letting go and re-berthing after returning from ballast water exchange).
c. Assuming this fee will be charged again upon re-entry to the port.
d. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
e. Cost of running the ballast pumps for the duration of the de-ballast. (This includes additional maintenance).

There may be an additional cost with this Option caused by any delay of the vessel if the berth is not immediately available upon the vessel's return to port (i.e., another vessel has arrived and taken up the berth). This is particularly so in the case of container vessels at busy terminals.

This Option also assumes that all vessels have a shore discharge ballast manifold retro-fitted and are able to part-load cargo while retaining all ballast on-board until berthed at shore facility.

Port of Portland - Option 1

Option 1
The vessel leaves the port and exchanges ballast at sea before returning to load.

Distance
12 nm (one-way from berth to nearest area of 60m depth).

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

         

Deadweight

 

45 262dwt

37 700dwt

 

Gross Tonnage

 

26 092t

26 162t

 

Charter Ratea.

 

$13 500

$19 500

 

Exchange timeb.

 

5hrs

33hrs

 

Pilotage Timec.

 

5hrs

5hrs

 

Tot. Voy. Timed.

 

56hrs

38hrs

 

Daily Fuel Cons.

 

24.9 t

28 t

 

Ball. Capacitye

 

20 368 m3

13 195 m3

 

Ball. P/p Cap.f

 

1 200 m3/hr

1 200 m3/hr

 

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete an exchange of ballast water where 3 times the volume of ballast water is pumped through the tanks.
c. Pilotage has been calculated from berth to 60m depth area just beyond the pilot boarding ground and back to the berth.
d. Time taken to exchange ballast plus pilotage time.
e. Approximate ballast capacity only. (Ballast carried will depend on individual design of the vessel).
f. Combined pumping capacity of both/all ballast pumps.

Port of Portland - Option 1 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

 

1 870

1 870

 

Moor/unmoor

 

2 126

2 126

 

Linesboata.

       

Tugsb.

 

5 088

5 088

 

Channel duesc.

       

Fuel ($130/t)d.

 

7 553

5 763

 

Voyage Cost

 

31 500

30 875

 

Exchange coste.

 

1 620

1 630

 
         

TOTAL

 

49 757

47 352

 

a. 1 lines boat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker.
b. 1 tug allowed for each of the first three categories, 2 tugs allowed for the crude oil tanker (tug charges calculated to include letting go and re-berthing after returning from ballast water exchange).
c. Assuming this fee will be charged again upon re-entry into the port.
d. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
e. Cost of running the ballast pumps for the duration of the exchange. (This includes additional maintenance).

Port of Portland - Option 2

Option 2
The vessel loads cargo to its marks or maximum stability criteria, returns to sea to dump all ballast, then returns to port to complete loading.

Distance
12 nm (one-way from berth to nearest area of 60m depth).

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

         

Deadweight

 

45 262dwt

37 700dwt

 

Gross Tonnage

 

26 092t

26 162t

 

Charter Ratea.

 

$13 500

$19 500

 

Discharge timeb.

 

17hrs

11hrs

 

Pilotage Timec.

 

5hrs

5hrs

 

Tot. Voy. Timed.

 

22hrs

16hrs

 

Daily Fuel Cons.

 

24.9 t

28 t

 

Ball. Capacitye

 

20 368 m3

13 195 m3

 

Ball. P/p Cap.f.

 

1 200 m3/hr

1 200 m3/hr

 

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete discharging full load of ballast.
c. Pilotage has been calculated from berth to 60m depth area just beyond the pilot boarding ground and back to the berth.
d. Time taken to dump ballast plus pilotage time.
e. Approximate ballast capacity only.
f. Combined pumping capacity of both ballast pumps.

Port of Portland - Option 2 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

 

1 870

1 870

 

Moor/unmoor

 

2 126

2 126

 

Linesboata.

       

Tugsb.

 

5 088

5 088

 

Channel duesc.

       

Fuel ($130/t)d.

 

2 967

2 427

 

Voyage Cost

 

12 375

13 000

 

Discharge coste.

 

540

543

 
         

TOTAL

 

24 966

25 054

 

a. 1 lines boat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker.
b. Calculated to allow 1 tug for each of the first three categories and 2 tugs for the crude oil tanker (tug charges calculated to include letting go and re-berthing after returning from ballast water exchange).
c. Assuming this fee will be charged again upon re-entry into the port.
d. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
e. Cost of running the ballast pumps for the duration of the de-ballast. (This includes additional maintenance).

There may be an additional cost with this Option caused by any delay of the vessel if the berth is not immediately available upon the vessel's return to port (i.e., another vessel has arrived and taken up the berth). This is particularly so in the case of container vessels at busy terminals.

Port of Portland - Option 3

Option 3
The vessel moves straight to regular cargo loading berth and discharges ballast directly to an on-shore facility while loading.

Discharge of ballast could take place at each berth which would enable vessels to carry out normal cargo operations. A pipeline would need to be installed around the port perimeter so that the ballast treatment facility may be accessed from each berth.

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

         

Deadweight

 

45 262dwt

37 700dwt

 

Gross Tonnage

 

26 092t

26 162t

 

Charter Ratea.

 

$13 500

$19 500

 

Discharge timeb.

 

17hrs

11hrs

 

Pilotage Timec.

 

2hrs

2hrs

 

Tot. Voy. Timed.

 

19hrs

13hrs

 

Daily Fuel Cons.

 

24.9 t

28 t

 

Ball. Capacitye

 

20 368200 m3

13 195200 m3

 

Ball. P/p Cap.f.

 

1 200 m3/hr

1 200 m3/hr

 

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete discharging full load of ballast.
c. Pilotage has been calculated from the station pier berth to the proposed ballast water reception facility at Coode Island and back to station pier.
d. Time taken for a return trip from facility back to furthest berth plus time taken to completely de-ballast.

Port of Portland - Option 3 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

 

1 870

1 870

 

Moor/unmoor

 

2 126

2 126

 

Linesboata.

       

Tugsb.

 

5 088

5 088

 

Channel duesc.

       

Fuel ($130/t)d.

 

2 967

2 427

 

Voyage Cost

 

12 375

13 000

 

Discharge coste.

 

540

543

 
         

TOTAL

 

24 966

25 054

 

a. 1 lines boat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker.
b. Calculated to allow 1 tug for each of the first three categories and 2 tugs for the crude oil tanker (tug charges calculated to include letting go and re-berthing after returning from ballast water exchange).
c. Assuming this fee will be charged again upon re-entry into the port.
d. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
e. Cost of running the ballast pumps for the duration of the de-ballast. (This includes additional maintenance).

This Option assumes that all vessels will have a shore discharge ballast manifold retro-fitted.

Port of Hastings - Option 1

Option 1
The vessel leaves the port and exchanges ballast at sea before returning to load.

Distance
22 nm (one-way from furthest berth within the port to nearest area of 60m depth).

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

         

Deadweight

 

45 262dwt

37 700dwt

101 900dwt

Gross Tonnage

 

26 092t

26 162t

65 094t

Charter Ratea.

 

$13 500

$19 500

$36 000

Exchange timeb.

 

51hrs

33hrs

45hrs

Pilotage Timec.

 

6hrs

6hrs

6hrs

Tot. Voy. Timed.

 

57hrs

39hrs

51hrs

Daily Fuel Cons.

 

24.9 t

28 t

61 t

Ball. Capacitye

 

20 368 m3

13 195 m3

35 665 m3

Ball. P/p Cap.f

 

1 200 m3/hr

1 200 m3/hr

2 400 m3/hr

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete an exchange of ballast water where 3 times the volume of ballast water is pumped through the tanks.
c. Pilotage has been calculated from berth to 60m depth area just beyond the pilot boarding ground and back to the berth.
d. Time taken to exchange ballast plus pilotage time.
e. Approximate ballast capacity only.
f. Combined pumping capacity of both ballast pumps.

Port of Hastings - Option 1 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

 

2 848

2 852

7 176

Moor/unmoor

 

1 800

1 800

1 800

Linesboata.

 

1 400

1 400

1 400

Tugsb.

 

51 200

57 160

57 160

Channel duesc.

       

Fuel ($130/t)d.

 

7 688

5 915

16 851

Voyage Cost

 

32 063

31 688

76 500

Exchange coste.

 

1 620

1 630

4 500

         

TOTAL

 

98 619

102 445

165 387

a. 1 lines boat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker.
b. 2 tugs allowed for each category of vessel (tug charges calculated to include letting go and re-berthing after returning from ballast water exchange).
c. Assuming this fee will be charged again upon re-entry into the port.
d. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
e. Cost of running the ballast pumps for the duration of the exchange. (This includes additional maintenance).

Port of Hastings - Option 2

Option 2
The vessel loads cargo to its marks or maximum stability criteria then moves to a berth designated for off-loading contaminated ballast into shore holding tanks, before returning to the original cargo berth to complete loading.

Distance
22 nm (one-way from Fawkner Beacon to nearest area of 60m depth).

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

         

Deadweight

 

45 262dwt

37 700dwt

101 900dwt

Gross Tonnage

 

26 092t

26 162t

65 094t

Charter Ratea.

 

$13 500

$19 500

$36 000

Discharge timeb.

 

17hrs

11hrs

15hrs

Pilotage Timec.

 

6hrs

6hrs

6hrs

Tot. Voy. Timed.

 

23hrs

17hrs

21hrs

Daily Fuel Cons.

 

24.9 t

28 t

61 t

Ball. Capacitye

 

20 368 m3

13 195 m3

35 665 m3

Ball. P/p Cap.f.

 

1 200 m3/hr

1 200 m3/hr

2 400 m3/hr

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete discharging full load of ballast.
c. Pilotage has been calculated from berth to 60m depth area just beyond the pilot boarding ground and back to the berth.
d. Time taken to dump ballast plus pilotage time.
e. Approximate ballast capacity only.
f. Combined pumping capacity of both ballast pumps.

Port of Hastings - Option 2 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

 

2 848

2 852

7 176

Moor/unmoor

 

1 800

1 800

1 800

Linesboata.

 

1 400

1 400

1 400

Tugsb.

 

51 200

57 160

57 160

Channel duesc.

       

Fuel ($130/t)d.

 

3 102

2 579

6 939

Voyage Cost

 

12 938

13 813

31 500

Discharge coste.

 

540

543

1 500

         

TOTAL

 

73 828

80 147

107 475

a. 1 lines boat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker.
b. Calculated to allow 1 tug for each of the first three categories and 2 tugs for the crude oil tanker (tug charges calculated to include letting go and re-berthing after returning from ballast water exchange).
c. Assuming this fee will be charged again upon re-entry into the port.
d. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
e. Cost of running the ballast pumps for the duration of the de-ballast. (This includes additional maintenance).

There may be an additional cost with this Option caused by any delay of the vessel if the berth is not immediately available upon the vessel's return to port (i.e., another vessel has arrived and taken up the berth). This is particularly so in the case of container vessels at busy terminals.

Port of Hastings - Option 3

Option 3
The vessel loads cargo to its marks or maximum stability criteria then moves to a berth designated for off-loading contaminated ballast into shore holding tanks, before returning to the original cargo berth to complete loading.

Distance
The Port of Hastings has three berth areas. Reception facilities could
therefore be provided at an additional berth constructed in one area This would require a shift of ship from each of the berth areas to the designated de-ballasting berth and back again.

A. Background Information

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

Deadweight

 

45 262dwt

37 700dwt

101 900dwt

Gross Tonnage

 

26 092t

26 162t

65 094t

Charter Ratea.

 

$13 500

$19 500

$36 000

Discharge timeb.

 

17hrs

11hrs

15hrs

Pilotage Timec.

 

3hrs

3hrs

3hrs

Tot. Voy. Time

 

20hrs

14hrs

18hrs

Daily Fuel Cons.

 

24.9 t

28 t

61 t

Ball. Capacityd.

 

20 368 m3

13 195 m3

35 665 m3

Ball. P/p Cap.e.

 

1 200 m3/hr

1 200 m3/hr

2 400 m3/hr

a. Daily Rate ($AUD) vessel owner/manager charges for use of the vessel. This cost includes crew, maintenance and running costs, repairs etc., but does not include fuel.
b. Time taken (in hours) a vessel will take to complete discharging full load of ballast.
c. Pilotage has been calculated from the station pier berth to the proposed ballast water reception facility at Coode Island and back to station pier.
d. Approximate ballast capacity only.
e. Combined pumping capacity of both ballast pumps.

Port of Hastings - Option 3 Itemised Costs

B. Itemised Costs

 

Vessel Category

 

Container V/L

Bulk Carrier

Product Tanker

Crude Tanker

 

Charges ($AUD)

Pilotage

 

2 848

2 852

7 176

Moor/unmoor

 

1 800

1 800

1 800

Linesboata.

 

1 400

1 400

1 400

Tugsb.

 

51 200

57 160

57 160

Channel dues.

       

Fuel ($260/t)c.

 

405

455

991

Voyage Cost

 

11 250

11 375

27 000

Discharge costd.

 

540

543

1500

         

TOTAL

 

69 443

75 585

97 027

a. 1 lines boat (one man) for each of the first three categories, 2 lines boats (4 men) for the crude oil tanker.
b. Calculated to allow 1 tug for each of the first three categories and 2 tugs for the crude oil tanker (tug charges calculated to include letting go and re-berthing after returning from ballast water berth).
c. Fuel cost excluding tax. ($130 AUS/tonne - This is subject to market variation).
d. Cost of running the ballast pumps for the duration of the de-ballast. (This includes additional maintenance).

There may be an additional cost with this Option caused by any delay of the vessel if the berth is not immediately available upon the vessel's return to port (i.e., another vessel has arrived and taken up the berth). This is particularly so in the case of container vessels at busy terminals.

This Option also assumes that all vessels have a shore discharge ballast manifold retro-fitted and are able to part-load cargo while retaining all ballast on-board until berthed at shore facility.

Top Of Page

Committee Home PageTable Of ContentsPrevious PageNext Page